Presentation by Jim Goldsmith

Board of Selectmen's Meeting

Approved 4/12/05

 

Committee members in attendance: Jim Goldsmith, Bob Levin, Craig Edwards, David Gordon, Marcia Leibman, Marilyn Kahn, and Melissa Mills

 

After thanking the Board for inviting him to update the Selectmen on the status of the committee's work thus far, Jim Goldsmith provided an overview of the committee's concerns about abating the Wilber building and clarified several points regarding redevelopment of the building and the site.

 

In general, Jim conveyed that the committee believes that the building should be abated sooner than later.  Beyond that, he noted that estimates for removing hazardous materials in 2002 were in the approximately $300,000 range and that, with inflation since then, were now likely in the approximately $350,000 range.

 

In response to a question on this issue, Ben Puritz said he believes that the building itself is insured for replacement value and that he wasn't sure about coverage for hazardous waste removal; he will check the Town's insurance policy to confirm the details.  In response to a question from Selectman Bill Heitin regarding how the cost increase since 2002 has been "tested," Jim said that conversations with three developers suggested that costs had risen roughly to the level that he cited.  Bill urged the Wilber Redevelopment Committee to move forward with a "cost with, cost without" clause concerning abatement in the RFP that the committee is developing.

 

Both Bill Heitin and Selectman Joe Roach agreed that it makes sense to wait until the Fall 2005 Town Meeting to address the issue of abatement.  If responses to the RFP indicate that it would be financially preferable for the town to abate the building itself, rather than have a developer do it, then the two Selectmen would be willing to support an abatement article at that time.  Ben added that work on an abatement contract could proceed almost immediately upon approval and that, even though weather conditions wouldn't be optimal, could still proceed fairly easily in November and December 2005.

 

In response to a question from Jim, the Selectmen confirmed that they would like to see the committee develop a plan for redeveloping the entire site, not just for redeveloping the building.  The Selectmen also expressed a strong preference for maintaining the building, if possible, but noted that they would be willing to change their feelings on this issue, depending upon how developers respond to the RFP.

 

After Jim outlined some of the key points that will be featured in the RFP, the Selectmen urged the committee to move forward expeditiously in working with a consultant to flesh out the details of a narrative.  They also noted that they will vote on the issue officially on 4/19/05, when Selectman Grasfield will also be in attendance.

 

Finally, the Selectmen noted that the Wilber property is the most viable -- and essentially the only -- remaining site under consideration for siting the proposed septic system to serve the Town Center.  They acknowledged that the siting of such a facility could reduce the overall acreage available for redeveloping the parcel, and they expect that the study of water issues on the site will be completed within two months, if not sooner.

 

Repsectfully submitted,

David Gordon